Scope
Insulated HVAC ductwork, fire-fighting mains, cable tray and MEP fit-out across the warehouse
We delivered the mechanical and electrical installation across the facility's steel-framed warehouse and dock areas. Scope covered long runs of insulated supply ductwork with diffusers and fan-coil units suspended from the roof steel, red fire-fighting mains and sprinkler branches, perforated cable tray and conduit routing, and air curtains over the loading dock doors. The work was carried out from boom lifts and mobile scaffolding while the building fit-out progressed.
- Duration
- 13 months
- Location
- Jeddah/Makkah